McMoRan Bayou Carlin

Client: McMoRan Oil & Gas
Type: 50 mcfd Gas Facility, 195 X 35 Barge

(3) 1500 bbls. Tanks for oil and water storage
18,000 feet of 8"/S80 pipeline
(2) Underground bores. One was 4,800 feet and the second was 3,000 feet.

Petro Construction Management provided Project Management, Construction Management, Cost Tracking, and Procurement of materials and vendor surveillance on the skid packages.

Black Bay Central Facility

Client: Helis Oil & Gas
Location: Black Bay field
Type: 3 six-pile & 1 four-pile single level steel structures
Elevation: (+)40 ft above sea level
Production: 5,000 BOPD with 50% water cut

$55 million rebuild of full production facility for the entire Black Bay field. Facility included separation, oil treating and dehydration; LACT; compression; gas dehydration; gas lift system; gas sales; produced water injection; 32 man quarters; and desanding & de-oiling hydrocyclones for 80,000 BWPD.

Petro Construction Management provided Construction Management, Procurement, Inspection for the demolition and Rebuild of the consolidated production facilities and pipelines.

MC 365 Facility Upgrades

Client: Eni - Houston, TX
Location: MC 365A
Description: Facility Upgrades

Platform MC 365 is being converted to a gathering station with multiple sub-sea tie backs. This will entail major structural and piping modifications which will include removal of a 200 ton module, installation of a 900 ton production module, 600 ton compressor module and 70 ton methanol tank. This project will entail design and engineering of all modules, coordinating construction activities as well as all I&E activities and correspondence between the customer and the fabricator.

The Construction Managers review all safety procedures and regulations to ensure all safety procedures are followed. They review the welding qualifications and procedures. Ensure the use of proper material from vendor and traceability of all material. Monitor schedules and percent complete of fabrication. Ensure x-ray procedures are followed and maintain logistics. Construction Managers also ensure paint meets all specifications.

Key Features:

  • JSA
  • Daily Report
  • Construction Management
  • Q.C.
  • Procurement

MC 365A Vessel Fabrication

Client: Eni - Houston, TX
Location: MC 365A
Description: Vessel Fabrication

Petro Construction Management will facilitate production needs for Eni and multiple partners in building multiple vessels to produce more flow. This will entail building multiple vessels of various thicknesses, coordinating all aspects of fabrication and correspondence between customer and fabricator.

The Construction Managers review all welding qualifications and procedure. Review all Q.A./Q.C. procedure of vendor. Ensure use of right material from vendor and traceability of all material. Check all dimensions prior to cutting and fitting of penetration. Ensure all internals are proper size and properly located. Monitor schedules and percent complete of fabrication. Ensure welding procedures are followed through out fabrication. Ensure X-Ray/UT procedures are followed. They also make sure paint meets all specifications.

Key Features:

  • JSA
  • Daily Reports
  • Construction Management
  • Q.C. 
  • Procurement